— CARBON PROJECTION FROM ENERGY USE EAp1 Required
能源使用碳排放预测 EAp1 必须满足
To provide a baseline operational carbon emissions projection from energy use and to increase carbon literacy at the project level and throughout the real estate industry.
提供基于能源使用的运营碳排放基线预测,并在项目层面及整个房地产行业提升碳认知。
Achievement Pathways Points Existing Buildings N/A Operational Carbon Projection AND Building Performance Standard Business-as-Usual Projection Using the annual energy use data submitted, the project’s current grid data, and the project’s location, USGBC will generate a 25-year “business-as-usual” (BAU) projection of the project’s carbon emissions, including a comparison with a straight-line reduction. Provide a high-level estimated end-use breakdown as shown in
运营碳排放预测 以及 建筑性能标准 常规情景预测 利用提交的年度能源使用数据、项目当前的电网数据及项目区位,USGBC 将生成项目碳排放的 25 年"常规情景"(BAU)预测,包括与线性削减的对比。提供如表 1 所示的高层级终端用途分解估算。
Table 1.
表 1. 终端用途分解估算
Table 1. Estimated End-Use Breakdown End Use Electrical Used (Y/N) Fuel Used (Y/N) and Type Total Electrical Use (%) Total Fuel Use (%) Site Energy Use (%) Space heating Water heating Cooking Space cooling Lighting Plug, process, and other AND Building Performance Standard Business-as-Usual Projection Projects subject to a carbon-based or energy use intensity (EUI)-based building performance standard (BPS) must create an ordinance-specific 25-year BPS-BAU projection with an overlay of the BPS caps. For EUI-based BPS, the BPS-BAU must be an energy BAU, and for carbon-based BPS, the BPS-BAU must be a carbon BAU that reflectsing the electrical carbon coefficients as defined in the ordinance. If applicable, calculate the assessed annual fines or fees that will apply for exceeding the caps and the cumulative fines or fees over the 25-year period. The owner or owner's representative must attest that they have reviewed the project’s BAU and fee projections.
终端用途 | 用电(是/否)| 燃料类型及是否使用 | 总用电占比(%)| 总燃料占比(%)| 站点能耗占比(%)
空间供暖 | 水加热 | 烹饪 | 空间制冷 | 照明 | 插头、工艺及其他
以及 建筑性能标准 常规情景预测 受基于碳或基于能源使用强度(EUI)的建筑性能标准(BPS)约束的项目,必须创建针对该法规的 25 年 BPS-BAU 预测,并叠加 BPS 上限。对于基于 EUI 的 BPS,BPS-BAU 必须是能源 BAU;对于基于碳的 BPS,BPS-BAU 必须是碳 BAU。