MINIMIZED SITE DISTURBANCE
最小化场地扰动
SSp1 Required / 必需
Impact Area Alignment
☑ Decarbonization
☑ Quality of Life
☑ Ecological Conservation and Restoration
影响领域:脱碳 / 生活质量 / 生态保护与修复
INTENT / 目的
To minimize the effects of construction activities on previously undeveloped sites, in order to protect habitat, preserve topsoil, limit construction pollution, and manage the project site to reduce compaction.
最大限度减少施工活动对已开发场地的影响,以保护栖息地、保留表层土、限制施工污染,并通过场地管理减少土壤压实。
REQUIREMENTS / 要求
Do one of the following:
执行以下任意一项:
Option 1. Previously Developed Site
Locate all development on a previously developed site.
所有开发均选址于已开发场地。
Option 2. Disturbance Boundary
Establish a construction disturbance boundary on the site for all construction activity and show the boundary on all civil and site drawings. Select and implement strategies in three of the following categories:
为所有施工活动设定施工现场扰动边界,并在所有市政和场地图纸上标出。从以下类别中选择并实施其中三类的策略:
- Land Preservation — Limit disturbance to 40 feet (12 meters) beyond the building perimeter; 10 feet (3 meters) beyond surface walkways, patios, surface parking, and utilities less than 12 inches (30 centimeters) in diameter; 15 feet (4.5 meters) beyond primary roadway curbs and main utility branch trenches; and 25 feet (7.5 meters) beyond constructed areas with permeable surfaces.
土地保护:将扰动范围限制在建筑周边 40 英尺(12 米)、步道/庭院/地面停车场/直径小于 12 英寸(30 cm)公用管线周边 10 英尺(3 米)、主干道路缘石和主管沟周边 15 英尺(4.5 米)、透水表面施工区域周边 25 英尺(7.5 米)以内。
- Topsoil Preservation — Stockpile and reuse the topsoil within the project's site boundary. The stockpiled topsoil must not be mixed with subsoil. Restore stockpiled topsoil to final grades in all areas not covered by buildings, structures, or pavement.
表层土保留:将表层土堆放并回用于项目场地范围内。堆放的表层土不得与底土混合。将堆放的表层土恢复至除建筑、构筑物和铺装外所有区域的最终标高。
- Construction Pollution Prevention — Stabilization: Initiate soil stabilization measures immediately after grading activities have temporarily or permanently ceased on any portion of the site. Structural Control: Use structural control practices in accordance with the U.S. EPA's NPDES Construction General Permit or local equivalent. Sediment Control: Use sediment control measures to prevent sediment from being tracked off-site.
施工污染防治:稳定化——场地任何区域土方作业临时或永久停止后,立即启动土壤稳定措施。结构控制——按EPA NPDES施工通用许可或等效标准实施结构控制。沉积物控制——防止沉淀物被带出场外。
- Limits on Site Disturbance — Do not disturb the following: greenfields; land within 50 feet (15 meters) of any water body; land within 100 feet (30 meters) of any wetland; land that includes prime farmland or unique farmland; land that is habitat for species listed as threatened or endangered.
场地扰动限制:不得扰动绿地、任何水体 50 英尺(15 米)内的土地、任何湿地 100 英尺(30 米)内的土地、基本农田或特殊农田、受威胁或濒危物种栖息地。