← 工具箱首页 | ← LEED v5 BD+C 评分体系

MINIMIZED SITE DISTURBANCE
最小化场地扰动

Required / 必需

Impact Area Alignment

☑ Decarbonization
☑ Quality of Life
☑ Ecological Conservation and Restoration
影响领域:脱碳 / 生活质量 / 生态保护与修复

INTENT / 目的

To minimize the effects of construction activities on previously undeveloped sites, in order to protect habitat, preserve topsoil, limit construction pollution, and manage the project site to reduce compaction.

最大限度减少施工活动对已开发场地的影​​响,以保护栖息地、保留表层土、限制施工污染,并通过场地管理减少土壤压实。

REQUIREMENTS / 要求

Do one of the following:

执行以下任意一项:

Option 1. Previously Developed Site

Locate all development on a previously developed site.

所有开发均选址于已开发场地。

Option 2. Disturbance Boundary

Establish a construction disturbance boundary on the site for all construction activity and show the boundary on all civil and site drawings. Select and implement strategies in three of the following categories:

为所有施工活动设定施工现场扰动边界,并在所有市政和场地图纸上标出。从以下类别中选择并实施其中三类的策略: