— MINIMIZE SITE DISTURBANCE SSp1 Required (prerequisite)
Ecological Conservation and Restoration · 生态保护与修复 SSp1 Required (prerequisite)
To limit construction-related disturbance to the site and to preserve existing native vegetation, healthy soils, and wildlife habitats from damage during building work.限制施工活动对场地的扰动,并在建设过程中保护场地内既有的原生植被、健康土壤与野生动物栖息地免受破坏。
Required for all projects. Demonstrate compliance through two linked components: (1) an Erosion and Sedimentation Control (ESC) plan that follows the U.S. EPA 2022 Construction General Permit (CGP), the EU Taxonomy DNSH Pollution Prevention criteria, or a locally equivalent and equally stringent standard, including exclusion zones for critical habitats and regular inspections; AND (2) a preconstruction site assessment identifying special-status vegetation (100% of which must be conserved), healthy plant communities (protected by physical exclusion zones), and invasive species (to be removed and not replanted). Only native or adapted, non-invasive vegetation may be installed.所有项目必须达标。需通过两项关联内容证明合规:(1) 水土流失控制(ESC)计划,遵循美国 EPA 2022 施工通用许可(CGP)、欧盟分类法 DNSH 污染防治要求或同等更严格的本地标准,包括为关键栖息地设置隔离区并定期巡查;以及 (2) 施工前场地评估,识别特殊状态植被(须 100% 保留)、健康植物群落(以物理隔离区保护)和入侵物种(须清除且不得再种植)。仅可种植原生或适应性、非入侵性的植被。
Applies to every site regardless of size, even plots under one acre; zero lot line sites may submit a narrative instead.ESC plan must conform to CGP, EU Taxonomy DNSH, or a local equivalent and include habitat exclusion zones plus inspections every 7 days or after 0.25 in. storms.Special-status vegetation defined by local, state, or federal entities must be conserved at 100%.Healthy habitats require physical exclusion zones; invasive species must be identified, removed, and never replanted.All planted vegetation must be native or adapted to the EPA Level III ecoregion and not currently listed as invasive. 适用于所有规模的场地,包括不足一英亩的地块;零退线项目可提交说明替代。水土流失控制计划须符合 CGP、欧盟分类法 DNSH 或本地等效标准,并包含栖息地隔离区,每 7 天或 0.25 英寸降雨后巡查。由地方、州或联邦定义的特殊状态植被必须 100% 保留。健康栖息地须设物理隔离区;入侵物种须识别、清除且不得再种植。所有种植植被须为原生或适应该地 EPA 三级生态区的非入侵物种。