— INTEGRATIVE PROCESS, PLANNING, and Restoration Integrative Process, Planning, and Assessments Prerequisite CLIMATE RESILIENCE ASSESSMENT IPp1 REQUIRED
气候韧性评估 IPp1 必要项
To promote a comprehensive assessment of observed, projected, and future natural hazards for climate resilience, aiming to enhance awareness of hazards, increase transparency of risks, reduce vulnerabilities, and ensure long-term safety and sustainability.
旨在推动对已观测、预测和未来自然灾害的全面评估以增强气候韧性,提高对灾害的认知、增加风险透明度、减少脆弱性,并确保长期安全与可持续性。
Climate and Natural Hazard Assessment Complete a climate and natural hazard assessment. As part of the assessment, identify observed, projected, and future natural hazards that could potentially affect the project site and building function. For the purpose of this prerequisite, hazards are site-specific natural hazards that include, but are not limited to, drought, earthquakes, extreme heat, extreme cold, flooding, hurricanes and high winds, hail, landslides, sea level rise and storm surge, tornadoes, tsunamis, wildfires and smoke, winter storms, and other relevant hazards (specify). Identify two priority hazards, at minimum, to address through proposed operations and maintenance strategies. For each priority hazard, the project team must assess and specify the following:
气候与自然灾害评估 完成气候与自然灾害评估。作为评估的一部分,识别可能影响项目场地和建筑功能的已观测、预测和未来自然灾害。就本先决条件而言,灾害指场地特定的自然灾害,包括但不限于:干旱、地震、极端高温、极端低温、洪水、飓风和强风、冰雹、山体滑坡、海平面上升和风暴潮、龙卷风、海啸、野火和烟雾、冬季暴风雪,以及其他相关灾害(请说明)。至少确定两个优先灾害,通过拟议的运营和维护策略加以应对。对于每个优先灾害,项目团队必须评估并明确以下内容:
• Intergovernmental Panel on Climate Change (IPCC) emissions scenario used,
• 所使用的政府间气候变化专门委员会(IPCC)排放情景,
specifying the shared socioeconomic pathways
明确共享社会经济路径
• Projected service life of the LEED project (e.g., fiscal year 2050 or 100 years)
• LEED项目的预计使用寿命(例如,2050财年或100年)
• Hazard level
• 灾害等级
• Hazard risk rating
• 灾害风险评级
• Exposure, sensitivity, adaptive capacity, vulnerability, and overall risk levels
• 暴露度、敏感性、适应能力、脆弱性及整体风险水平
• Potential impact on the project site and building function
• 对项目场地和建筑功能的潜在影响
Where possible, use the information from the assessment to inform the operations and maintenance of the project and describe how project-specific strategies were considered.
尽可能利用评估信息指导项目的运营和维护,并描述如何考虑项目特定的策略。