— ENHANCED COMMISSIONING EAc4 1–4 points
增强调试 EAc4 1–4 分
To further ensure that the building systems function as designed, and that they continue to maintain energy performance over time.
进一步确保建筑系统按设计意图运行,并随着时间推移持续保持能效性能。
Achievement Pathways Points Commercial Interiors 1–4
达标路径:1–4 分
Option 1. Enhanced Commissioning 1–2
选项 1. 强化调试(1–2 分) 和/或 选项 2. 基于监测的调试(MBCx)(1–2 分)。
AND/OR
选项 1. 强化调试(1–2 分) 业主须在设计前期或设计极早期指定一名独立的调试服务商(CxP)。按 ANSI/ASHRAE/IES Standard 202-2024《调试过程》对项目范围内的机械、电气、给排水、数据中心、工艺、建筑监测、外围护结构及可再生能源系统(含与基础建筑系统的互联)进行调试。CxP 还须:至少出席一次设计协调会议和至少两次施工里程碑会议讨论审查意见与调试;提供持续调试计划;入住期间审查培训材料以确认符合培训计划并确认培训已实施。若项目范围改造了 25% 及以上的外围护结构面积或 5,000 平方英尺(465 平方米)外围护结构,现场检测须按需包括 ASTM E1105/AAMA 501.2 渗水测试和 ASTM C1153/C1060 红外成像。
Option 2. Monitoring-Based Commissioning (MBCx) 1–2
和/或 选项 2. 基于监测的调试(MBCx)(1–2 分)
Path 1. Basic MBCx 1 OR
路径 1. 基本 MBCx(1 分) 建立流程与沟通机制,承诺实施持续调试流程,包括:识别关键系统与能源使用;建立监测系统与基准;记录设施运行方式;建立故障检测与诊断(FDD)系统;定期审查能源与系统性能;持续实施节能措施;确定再调试的触发条件;对负责运行人员进行持续培训;建立年度能耗与碳排放预算及监测机制。
Path 2. Enhanced MBCx 2
或 路径 2. 增强 MBCx(2 分) 满足路径 1 要求,并安装符合 ASHRAE 标准或等效的自动化故障检测与诊断(FDD)系统,覆盖 HVAC、照明与可再生能源系统;提供实时仪表板与报警;建立正式节能再投资机制;每季度进行性能审查;持续验证节能措施效果并记录。
Option 1. Enhanced C ommissioning ( 1–2 points) Owner must designate an independent commissioning provider (CxP) during pre-design or very early in the design phase. Comply with ANSI/ASHRAE/IES Standard 202-2024, “Commissioning Process” for mechanical, electrical, plumbing, data center, process, building monitoring, building enclosure, and renewable energy systems within the project scope of work (including any interconnection with base building systems). The CxP must comply with the following additional requirements:
AND/OR
Option 2. Monitoring-Based Commissioning (MBCx) (1– 2 points) PATH 1. BASIC MBCX (1 POINT) Process and communications Commit to implementing MBCx for a minimum of three years. Include all of the following:
• Attend at least one coordination meeting during the design phase and at least two milestone meetings during the construction phase to discuss review comments and commissioning.
• Provide an ongoing commissioning plan.
• During occupancy, review the training materials to confirm that they meet the training plan, and confirm that the training occurred. If the project scope includes alterations to 25% or more of the building envelope area or 5,000 square feet (465 square meters) of the building enclosure, then field testing for the building enclosure shall include the following if applicable:
• Water penetration testing per ASTM E1105 or AAMA 501.2, as appropriate.
• Infrared imaging per ASTM C1153 or ASTM C1060, as appropriate.
• MBCx plan: Develop an MBCx plan and include it in the current facilities requirements and operations and maintenance plan. The MBCx plan must describe: o Roles and responsibilities o Training of operations staff o A software technology description, including frequency and duration of trend monitoring. o An action plan for identifying, prioritizing, correcting, and verifying correction of operational errors. o Review and reporting criteria. At least annually, provide a summary report of trends, benchmarks, faults, energy savings opportunities, corrective actions taken, and planned actions.
• Energy information system (EIS): Have in place a remotely accessible platform with software functionality to perform smart analytics and visually present project electricity consumption and fuel consumption, excluding shared systems serving the project space. Tenant access to the building EIS is acceptable. Include the following functionality:
• Annual energy benchmarking of energy use intensities.
• Comparison of total project energy consumption and energy consumption of fuel and electricity to the prior interval annually and monthly.
• If electricity interval metering is required in EAp4: Energy Metering and Reporting, provide visualization and reporting of hourly total electricity and submetered data. For total tenant electricity, include an hourly loadshape and comparison of hourly electricity to the prior interval, and to the same interval of the prior year annually, monthly, weekly, and daily.
• Provide hourly monitoring and visualization of electric energy use for: o Commercial kitchen equipment in project spaces with more than 20 kW of rated capacity. o Process equipment in project spaces with more than 20 kW of rated capacity.
• Training: Train operations staff to use the EIS to proactively inform energy-efficient operations or confirm training occurred within the past six years. OR PATH 2. ENHANCED MBCX (2 POINTS) Comply with Path 1 and implement the following enhanced MBCx practices and software capabilities:
• Provide MBCx through a corporate MBCx program or contracted service. Fully coordinate the MBCx process between the space operations staff and the monitoring-based commissioning provider (MBCxP).
• Process and communications: The MBCxP process must include o Expeditious communication of major anomalies or faults identified by MBCxP to facilities staff. o At least quarterly, an MBCxP summary of anomalies and faults detected and communication with facilities staff to discuss and prioritize issues. o For projects with fault detection and diagnostics (FDD), training of operations staff in the use of FDD to proactively identify and correct building system issues for optimized system operation or a confirmation that training occurred within the past six years. Enhanced energy information system (EIS). Include the following additional functionality:
• Normalization of energy consumption
• Automated reporting of energy use anomalies
• Greenhouse gas emissions (GHG) emissions reporting
• Hourly metering and visualization of electricity for the following, if applicable: o On-site electricity generation o At least 90% of lighting power altered or installed in the project scope of work. o HVAC or refrigeration equipment with thermal energy capacity exceeding 900,000 Btu/hr (264 kW, 75 tons), or with rated fan power exceeding 75 hp (56 kW). o Electricity use for process equipment with thermal energy capacity exceeding 900,000 Btu/hr (264 kW, 75 tons) FDD for projects with large HVAC and refrigeration capacity. For total project installed capacity of either cooling systems, heating systems, or refrigeration systems exceeding 7,200 kBtu/hr (600 tons, or 2,110 kW), provide a remotely accessible FDD system that addresses at least 60% weighted by capacity of:
• Air-handling equipment, AND
• Large hydronic or commercial refrigeration equipment (chillers, boilers, etc.). The FDD system must be able to:
• Perform smart analytics and visually present FDD data.
• Direct link from reported fault to view relevant trend data.
• Sort and filter faults.
• Export fault reports (summary reports and detailed individual faults).
• Act as a data historian capable of storing critical trend data for at least three years.