← 工具箱首页 | ← LEED v5 BD+C 评分体系
Integrative Process,
Planning, and Assessments
整合过程、规划与评估
Climate Resilience Assessment
气候韧性评估
IPp1 Required 必要条件 New Construction 新建建筑 Core and Shell 核心与外壳
Impact Area Alignment
影响领域对应
Decarbonization 脱碳
Quality of Life 生活质量
Ecological Conservation and Restoration 生态保育与恢复
Intent 目的

To promote the comprehensive assessment of observed, projected, and future natural hazards for climate resilience with an aim to enhance awareness of hazards, increase transparency of risks, reduce vulnerabilities, and ensure long-term safety and sustainability.

旨在推动对已观测、预测及未来自然灾害的全面评估,以提升气候韧性——增强灾害意识、提高风险透明度、降低脆弱性,并确保项目的长期安全与可持续性。

Requirements 要求
Achievement Pathways
达标路径
Points
分值
New Construction and Core and Shell
新建建筑及核心与外壳
N/A
Climate and Natural Hazard Assessment
气候与自然灾害评估

Complete a climate and natural hazard assessment.

完成一份气候与自然灾害评估。

As part of the assessment, identify observed, projected, and future natural hazards that could potentially affect the project site and building function. Address site-specific natural hazards, including, but not limited to, drought, extreme heat, extreme cold, flooding, hurricanes and high winds, hail, landslides, sea level rise and storm surge, tornadoes, tsunamis, wildfires and smoke, winter storms, and other relevant hazards (specify).

评估内容须包括识别已观测、预测及未来可能影响项目场地与建筑功能的自然灾害。需针对场地特定自然灾害进行分析,包括但不限于:干旱、极端高温、极端低温、洪涝、飓风及大风、冰雹、山体滑坡、海平面上升及风暴潮、龙卷风、海啸、野火与烟雾、冬季风暴,以及其他相关灾害(需注明)。

Identify two priority hazards, at minimum, to address through proposed design strategies. For each priority hazard, the project team must assess and specify the following:

至少确定两项优先灾害,并通过拟定的设计策略加以应对。对于每项优先灾害,项目团队须评估并明确以下内容:

  • Intergovernmental Panel on Climate Change (IPCC) emissions scenario used, specifying the shared socioeconomic pathways
    使用的政府间气候变化专门委员会(IPCC)排放情景,并注明所采用的共享社会经济路径(SSP)
  • Projected service life of the LEED project (e.g., fiscal year 2050 or 100 years)
    LEED 项目的预期使用寿命(例如:至财政年度 2050 年或 100 年)
  • Hazard level
    灾害等级
  • Hazard risk rating
    灾害风险评级
  • Exposure, sensitivity, adaptive capacity, vulnerability, and overall risk levels
    暴露程度、敏感性、适应能力、脆弱性及总体风险水平
  • Potential impact on the project site and building function
    对项目场地及建筑功能的潜在影响
  • Potential impact on the project site during construction
    对项目场地施工期间的潜在影响

Where possible, use the information from the assessment to inform the planning, design, and operations and maintenance of the project and describe how project-specific strategies were considered.

在条件允许的情况下,应将评估所得信息用于指导项目的规划、设计及运营维护,并说明如何考虑并纳入项目特定的应对策略。